What does the cone of uncertainty say? (Longer forecasts are less certain)
When multiple teams are working on the same product, one person can be a member of more than one Development Team ? (Yes)
When multiple teams are working on the same product, each team should have its own Definition of Done? (False)
What is a benefit of having tests in the Definition of Done? ( Increases transparency)
How often should the satisfaction of the customer be measured? (Frequently)
What does a trend line through a release burn-down chart indicate? (When the remaining work will likely be completed if nothing changes in the Product Backlog or the Dev Team)
Who can attend the Daily Scrum meeting? (Anyone)
The purpose of each Sprint is to release a piece of working software. (False)
Only the Development Team can compose the Definition of Done. (False)
Scrum can be used for sustaining complex products (True)
The performance of the Sprint should be measured at least (Once a day)
When multiple teams are working on the same product, their Sprints should start and end at the same time. (False)